COSLRigmar 5 year SPS

COSLRigmar was successfully jacked down at Eldfisk FTP on May 9 heading for Keppel Verolme Shipyard in Rotterdam.

The voyage down to Maas Pilot Station took 60 hours, but due to the dependence of high tide to enter the channel, the rig arrived at Keppel Verolme on 12 of May at 24:00 hours and was moored alongside the quayside. The following morning she was successfully docked according to plan, and the dock was empty for water at 17:30 hrs. The yard started the work immediately and has a very proactive and "aggressive" attitude to make sure the work is completed as soon as possible.

The scope of work is briefly related to inspection of legs and spud cans, steel repair in tanks, replace anodes, change out HVAC for machinery spaces and replace switch boards etc.

The duration of the yard stay is estimated to 6 weeks. 

 

 

 