COSLPioneer finished at Glitne field

The operations went as planned without serious incidents or accidents.

Unfortunately, the well was "dry" so the production completions of the well was canceled. COSLPioneer completed the anchor handling at Glitne and sailed to Åmøy on Wedensday 6 June. In addition to the crew change there has been performed a DP test and a lot of cargo handlig as part of the preparations for the up coming operations at Brugdan II, at the Faroe Islands. 

Today (12.6, 08:10 hrs) COSLPioneer left Åmøy for her voyage to the location of Brugdan II. ETA: Saturday the 16 June.

The Brugdan II operation will be the first DP operation performed by COSLPioneer at a water depths of 459 meters. The duration of the project is estimated to approx. 4-5 months.

COSL Drilling Europe will be represented in the Capital Torshavn during the operations at the Faroes.